By Andreas Christofides — licensed Florida general contractor CGC1537881, 20+ years of experience. Published September 2, 2026
Almost always, yes. You need a permit to remodel a kitchen or bathroom in Naples the moment the work touches plumbing, electrical, mechanical, gas or structure — which is nearly every real remodel. The useful questions are whose permit, what triggers it, and how much the state’s new $7,500 exemption changes in Collier County. Very little, as it turns out.
A Naples mailing address does not tell you which building department has jurisdiction. Three separate authorities issue permits in this area:
Collier County applications go through the county’s CityView online portal. Submitting to the wrong jurisdiction is not corrected quietly — it is rejected, and the clock starts again. Confirm jurisdiction from the parcel, not the mailing address.
The trades are what pull a project into permitting, not the room and not the budget. In practice a permit is required when the work involves:
What generally does not require a permit on its own: cabinets replaced in the same footprint, new countertops, tile over an existing substrate, paint, and swapping a fixture for one in the same location. Few remodels stop there.
Florida House Bill 803 took effect July 1, 2026. It requires local governments to exempt the owner of a single-family dwelling, or that owner’s contractor, from obtaining a building permit for qualifying work valued under $7,500. It has been reported as a break for homeowners. For a Naples kitchen or bathroom, it usually is not, for four reasons.
It excludes the five trades that define a remodel. The exemption does not apply to electrical, plumbing, structural, mechanical or gas work. That leaves cosmetic scope — cabinetry, flooring, drywall finishing, paint — precisely the work least likely to need a permit anyway.
It excludes flood hazard areas. It does not apply to property located partly or entirely within a Florida Building Code flood hazard area, and large parts of coastal Collier County, including Naples and Marco Island, fall inside mapped flood zones.
It is written for single-family dwellings. Condominiums and townhomes are not covered, which removes a substantial share of the Naples market outright.
Projects cannot be split to fit under it. The law prohibits dividing a larger project into smaller pieces to get beneath the $7,500 threshold, and a written request documenting the nature and value of the work is still required. It is not a self-declared allowance.
The same bill did bring useful changes: a shorter review window for certain single-family permits under $15,000, a requirement that departments flag incomplete applications within a set number of business days, and a rule that an association cannot require a building permit as a prerequisite for its own architectural review — worth knowing if your board has been asking for a permit number before it will look at your drawings.
Fees vary by jurisdiction and scope; the schedule impact matters more. Rough-in plumbing and electrical must be inspected before walls close, so the tile setter cannot start Monday because the drywall went up Friday. A schedule with no inspection holds in it will slip.
Unpermitted work rarely causes a problem during construction. It causes one later.
Two independent processes, different reviewers, different timelines — and in a Naples community you almost always need both. The board reviews impact on the building and the neighbors: work hours, elevator use, noise, the seasonal window many associations enforce. The building department reviews code compliance. Board approval usually has to come first, because associations frequently require the approved drawings to be the ones filed. Our guide to condo renovations in Naples covers the approval package in more detail, and what is actually possible when removing a wall in a condo walks through the structural side.
Yes, in almost every case. Moving plumbing, adding or altering circuits, changing range-hood venting or running a gas line all require one, and most kitchen remodels do at least one of those. A cabinet-and-countertop replacement in the identical footprint, with no trade work, may not.
Almost certainly not. It excludes plumbing, electrical, structural, mechanical and gas work, and a bathroom remodel is defined by plumbing. It also does not apply in flood hazard areas or to condominiums, and the work cannot be split to fit under the threshold.
Florida allows an owner-builder permit for work on your own property under specific conditions, and Collier County has its own requirements around it. It also makes you responsible for the code compliance, inspections and liability a licensed contractor would otherwise carry.
Your general contractor, under their license — they are accountable to the building department, schedule the inspections and close the permit out. Ask for the permit number once it is issued, and for confirmation that it was finalled when the job is done.
Whether a permit applies, which department issues it, and what the association needs first are all answerable in a single visit, before anyone spends money on drawings. GC Pro West is a Florida Certified General Contractor (license CGC1537881) with 20+ years of experience, and we handle permitting and association approvals as part of the project across Naples and Marco Island, including Pelican Bay and the surrounding gated communities.
Planning a kitchen or bathroom remodel in Naples and want to know what it will require? Request a free consultation or call 239-307-8020.
Planning a project?
See our Naples remodeling cost guide, or explore kitchen remodeling, bathroom renovation, and condo renovation in Naples. More guides on the blog.